Wednesday, December 3, 2014

Project Progress Update

The Contractor has been working on the end of Felt Street and into the Villa Santa Cruz mobile home park over the last couple weeks. They plan to have the remainder of open cut installation completed in the mobile home park by the end of this week, weather permitting.
Once work in the mobile home park is completed, the Contractor will move to Brommer Street to complete the small portion of work in the area. They will also be lining the existing sewer between the end of Felt Street and the pump station on Richmond Drive.

Once all new sewer installation work is completed, the Contractor will begin the process of abandoning the old sewer lines and manholes that will be taken out of service, completing final paving, and lining of new and existing manholes.

We thank you for your continued patience as the project continues to move forward towards completion!