Construction Schedule Update

The Contractor continues to make good progress on the overall installation of the new sewer. They have completed the trenchless installation of the new sewer at the railway crossing near Simpkins Swim Center on 17th Avenue, and will be paving this area for the remainder of the week. There will be no work on 17th Avenue over the next several weeks in consideration of the start of the new school year.
Overall Sewer Installation Progress as of 8-20-14

The Contractor will return to Felt Street on Friday and will continue sewer installation up Felt Street toward 17th Avenue over the next several weeks. Updates will be provided as work progresses.