Sewer Installation at Railroad Crossing Continues on 17th Avenue

Progress continues on the sewer installation at the railway crossing on 17th Avenue near Simpkins Swim Center and also on Felt Street and 24th Avenue. For the remainder of the week, the Contractor will focus on the sewer installation at 17th Avenue. As a reminder, below is the work zone which is controlled by flaggers:
Work Zone at 17th Avenue Near Simpkins Swim Center
The working hours in this area are 8:30am to 7:30pm in an effort to complete the sewer installation in this area before the beginning of the school year.

Please feel free to call our project phone line (831) 708-8285 if you have any questions or concerns. Thank you for your continued patience and understanding during construction.