The Contractor is continuing work on 17th Avenue near Simpkins Swim Center at the railway crossing. In an effort to complete this portion of the work prior to the beginning of the school year, working hours on 17th Avenue have temporarily been extended to between the hours of 8:30am and 7:30pm, Monday through Friday.

The Contractor also has a second crew finishing up sewer lateral tie-ins on 24th Avenue and will resume installation of pipe to the end of 24th Avenue and continuing on to Felt Street through the end of this week. Working hours in this area are 8:30am to 5:30pm, Monday through Friday.